Q & A with ISG and their development of Monmouth Leisure Centre

Alliance Leisure worked with ISG to build a 25m swimming pool and spa within the existing structure of a sports hall. We talk to Mark Gibson, ISG site manager, about this impressive feat of construction engineering.

Q. How did you come to be involved in the scheme?

Alliance Leisure appointed us as principle build contractor to refurbish and extend Monmouth Leisure Centre in South Wales. The £7.4m project was the 18th scheme that Alliance Leisure had awarded us through the UK Leisure Framework. It has certainly been one of the most complicated, but anything is possible with the right team and procurement approach.

Q. What was the brief?

Monmouthshire County Council wanted to future-proof the centre’s facilities while meeting demand in under-represented markets in the area such as health and wellbeing and children’s play. The project would provide a raft of new facilities including a new gym, studios, a toning suite, children’s play area and café. The town had been without a public pool for some years, so the council also wanted the development to include a 25m pool and a spa.

Q. What made the project so complex?

The leisure centre shares its site and some of its facilities with Monmouth Comprehensive School. At the time of the redevelopment, a new home for the school was being built to the left of the leisure centre. With the existing school sitting to the right of the centre, the only place to put the pool was in the leisure centre’s sports hall.

The combination of the location of the leisure centre between the old and new schools, just one access road into the site and 2,000 pupils passing the live construction site every hour made the logistics of the project hugely challenging. We always knew this was going to be a difficult project, but logistically it was more challenging than projects I have run in central London.

Before work could begin on the pool, we had to erect a temporary sports hall to accommodate the school and community while the project was ongoing. We built temporary facilities for the London 2012 Olympics, so were able to construct a high spec, four-court hall in six weeks that was bigger and better than its permanent predecessor.

Q. How did you overcome the challenges?

We worked with Alliance Leisure to develop innovative solutions to a number of challenges caused by the logistical constraints of the site. A single narrow strip – 1.5m at its thinnest point – provided the only access to the hall. We had to remove a section of the elevation to get the necessary piling equipment and plant machinery into the building to facilitate the work.

We stripped the building back to its shell and treated with spray-on insultation to protect and seal the hall and prevent any impact onto the adjoining dry site.

Monmouth has soft ground as well as a high water table, which called for some innovative temporary works solutions and creative piling designs to support the new swimming pool.

The existing concrete slab in the sports hall needed to be broken out before excavation work could commence. However, traditional temporary works solutions could not be implemented due to logistical constraints. An innovative solution was developed to install a king-post wall to form a u-shape around the deep end of the pool. I-beam posts were driven into the bedrock at 1.2m intervals and then railway sleepers were slotted between the beams on top of one another to form a sacrificial support structure. Another bespoke element saw the use of steel tube piles instead of CFA piles. This solution minimised noise and vibration and reduced the volume of arisings produced.

We also used a sprayed concrete system to cast the slab and walls of the pool. Rejecting a typical formwork solution, again due to logistical constraints and to provide a quicker application, we used a specialist lightweight concrete mix. This unorthodox approach delivered significant time savings – with the entire pool completed within a week and designed, built and tested to BS EN 1992-3:2006 standards.

Q. What made this a successful project?

Construction is not about putting blocks on top of each other; it’s about creativity, innovation and changing perceptions. Thanks to our successful partnership with Alliance Leisure, we were able to take a pragmatic approach to the project, value engineering as and when necessary. This included redesigning the spa area to make better use of the space and include a treatment room. You can only make these types of improvements on projects where you have such close collaboration.

To view more details on the Monmouth development visit our case studies page here

Alliance Leisure Service Appoints Business Development Manager to Drive Growth

Alliance Leisure Services (ALS) drives growth in the North with the promotion of Tom Gardner to the Business Development team. With seven years’ experience within ALS, Tom has led the National Impact Sales Team whilst acting as a Strategic Partnership Manager to clients across the UK.

The new role sees Gardner move seamlessly from ALS’s client support division, TA6, to business development, where he will help support and grow ALS’s portfolio of public sector partners with a view to regenerating leisure provision in the North of the UK. The varied role will see him work with ALS clients to deliver business planning, feasibility studies as well as the design, build and delivery of leisure facilities.

James Foley, Commercial Director of Alliance, said: “We are delighted to welcome Tom to the Business Development team to help drive our activity in the region. Tom has considerable experience of the client support side of the business, so moving into business development is a natural next step for him and will help us accelerate our growth in the North of England and Scotland.”

Tom Gardner comments: “I am hugely grateful for the opportunities that working for such a progressive company as Alliance has provided me. I have fulfilled a variety of roles, thoroughly enjoying each challenge and look forward to developing further in the Business Development team. This is an exciting avenue for me. I am hugely passionate about our sector, improving the health of our nation and being able to assist in the development of leisure provision is, for me, something to be proud of.”

Haverhill Transformation Completed

Alliance Leisure have successfully completed a £1.5m transformation of Haverhill Leisure Centre for West Suffolk Council and Abbeycroft Leisure.  The project has already been hailed a huge success, delivered on time and within budget via the UK Leisure Framework.

New users of all ages packed out the new facilities on opening weekend. The centre remained open to the public throughout the 7 month build project which included:

  • XHeight Adventure Climbing
  • Soft Play
  • Indoor Parkour
  • new enlarged Gym
  • Studios
  • Changing Rooms
  • Paddy & Scott’s café
  • Self-Centre Health & Wellbeing facility, including 3 x Studios and 7 x Treatment Rooms
  • New Reception & circulation areas
  • New Sports Hall floor for the local school!

 

Watch this space for more photos of this outstanding development, and the full story…

Phase 2 Starts at Exmouth Leisure Centre

Swimming_1_ELC_News_BlogExmouth Leisure Centre’s phase 2 development is now underway as part of the £800k investment in the facility.  This phase will see the refurbishment of the wet changing areas and is part-funded by £180k from Sport England and £180k from East Devon District Council.  LED Leisure Management Ltd are providing the remaining funds.

The scheme is due to complete in March 2017.

For more details click here

 

Work Starts at Bradley Stoke Leisure Centre

Work has started today on the £3.6m investment at Bradley Stoke Leisure Centre with construction partner Createability. Alliance Leisure were appointed as the development partner for South Gloucestershire Council and Circadian Trust and the Bradley Stoke project will be the first in this partnership.
bradley stoke lc
The development will include:
– 17-Wall XHeight climbing facility
– Large adventure play
– 12-Station toning suite
– Larger Group Exercise and Multi-Purpose Studios
– Gym Expansion
– Party Rooms
– Additional Parking Spaces
– Refurbished Changing Rooms
– Soho Café Expansion

The project is being phased to minimise disruption to the centre:

Phase 1:
Conversion of 2 squash courts to 2 large studio’s
Refurbishment of the female dry changing rooms
Completes early May 2016
arrows

Phase 2:
Conversion of 2 courts from the 6 court hall to climbing and play
Refurbishment of the male changing rooms
Gym extension
Café extension
Car park expansion
Façade upgrade
Completes October 2016
arrows

Phase 3:
Conversion of existing soft play to toning and 2 party rooms
Refurbishment of existing studio’s
Completes January 2017

National Networking Event Comes to Scotland

Alliance Leisure will be hosting another of its national events in Scotland on the 11th November at Xcite Craigswood.  This workshop will bring together senior leisure managers to discuss a range of relevant topics as well as receive updates from ukactive and Alliance about their observations covering the whole of the UK.

The day will commence at 10am and finish around 3pm.  For more information or to book your place please contact John Leaver on 07909988532 or email training@allianceleisure.co.uk

Click on the programme schedule below for full details of the day.

Networking event